Campus Construction News
🚧 •..>𝒻𝓪Ĺ𝓵 𝐜𝕠𝓝Ⓢ𝓉ᖇ𝓾𝕔t𝐈Ø𝐧 ᵘⓟⓓΔ𝓉𝒆 week 2 <..• 👀
A 140,000 lb pump truck on campus Thursday means footings are in! It was quite a spectacle to see such an amazing machine stretch out 200+ feet to take cement just where it was needed. Can’t wait to see what’s next!
Fall Construction: Sept. 25, 2026, week 1.2
This week needs a second construction update with so much that happened in just a few days. After demo wrapped up Wednesday, from gravel to cement, the 130-ft conveyor truck was stretched to its limit all day Thursday just to reach the corner of the courtyard, but Schweighardt Concrete, LLC made it happen! We’re now ready for some greenhouse anchors to go on the footings, and if the rain, rain obeys and stays away, more cement and landscape rock next week!
Sept 21, Fall Construction Update, Week 1
Aug 7, 2026, Week 11
July 17, 2026, week 8
July 10, 2026, week 7
June 26, 2026 week 5
June 19, 2026: week 4
June 12, 2026: week 3
May 29-June 5, 2026: weeks 1-2
November 15
October 18
October 11
September 27
September 20
August 30
August 16
August 9
August 2
July 26
July 12
June 7
June 28
June 14
May 31
May 24
May 17
April 26
April 15
April 9
_________________________________
_________________________________
While the construction begins April 8, a low-key groundbreaking ceremony will happen Wednesday, April 10 at 1:30 pm. While it is not a private event, it will be a brief recognition that has not been publicized widely.
March 25
















































