Campus Construction News
🚧East side: A small portion of foundation walls on the south side are being completed. Concession building foundation was dug and footings were poured.
🚧Northwest side: Working to move the fiber optic line which provides internet and phone service to the building.
🌱Greenhouse: too wet again this week to pour concrete floors and sidewalks. 💦


🚧East side: Most of the footings and foundation walls are poured for the outer walls. Today they poured most of the inner footings (used 5 full concrete trucks!).
🚧Northwest side: Just demo so far. Our 400 hallway (industrial arts) will be closed Monday after school at the "old dumpster exit" to construct a temporary wall (back open Tues AM).
🌱Greenhouse: too wet this week to accomplish anything new 💦


π§ β’..>π»πͺΔΉπ΅ ππ πβπαπΎπtπΓπ§ Β Update Oct 30, week 6 <..β’ π
π§ β’..>π»πͺΔΉπ΅ ππ πβπαπΎπtπΓπ§ α΅ββΞππ Β Oct 23, week 5 <..β’ π
Fall Construction Update Oct 16, week 4
π§ β’..>π»πͺΔΉπ΅ ππ πβπαπΎπtπΓπ§ α΅ββΞππ Β Oct 9, week 3 <..β’ π
Oct. 2 Fall Construction, week 2
Photos from week 2
Sept. 25 Fall Construction 2026, week 1.2
Sept 21, Fall Construction Update, Week 1
Aug 7, 2026, Week 11
July 17, 2026, week 8
July 10, 2026, week 7
June 26, 2026 week 5
June 19, 2026: week 4
June 12, 2026: week 3
May 29-June 5, 2026: weeks 1-2
November 15
October 18
October 11
September 27
September 20
August 30
August 16
August 9
August 2
July 26
July 12
June 7
June 28
June 14
May 31
May 24
May 17
April 26
April 15
April 9
March 25